S4 have contracted land and secured a guaranteed 380kV grid connection at the new substation to be built by TenneT.
The necessary permit became irrevocable at the end of February 2025.
Additional studies will now be undertaken, the procurement process for all components will be initiated, and we will further detail the cable route. Additionally, we are exploring local opportunities to participate in an energy hub and establish an emergency power supply.
We are eager to begin the implementation and expect this battery to be connected to the electricity grid in 2027.